County road improvements coming to Wood Village

Multnomah County has a number of road projects coming to Wood Village, either in construction or in the design phase. Here’s a summary:

Construction in 2018

NE Sandy Blvd. Improvements (NE 230th to NE 238th)

Construction will start in spring 2018 to convert a section of Sandy Blvd. in Wood Village to a modern urban street with turn lanes. It will include pavement and drainage improvements, new sidewalks and bike lanes, lighting, and enhancements to existing bus stops.

  • Schedule: Utility relocation began in 2017. Roadway construction is expected to begin in late spring through mid-summer of 2018. Kodiak Pacific Construction is the contractor.
  • Traffic: Two lanes of traffic will be maintained at most times. Flaggers will direct traffic on a single lane at times, and there may be brief closure of driveways, with notice, during paving.
  • Website: www.multco.us/sandy

NE Arata Rd. Active Transportation Project

The project will build out a complete new streetscape on Arata Road in Wood Village between NE 223rd Ave. and NE 238th Dr. Improvements include:

  • 6-foot-wide sidewalk on the south side and a 10-foot-wide concrete shared-use path for pedestrians and bicyclists on the north side
  • Drainage improvement
  • Rectangular Rapid Flashing Beacon on NE 223rd Ave.
  • Add lighting, and repave road
  • Traffic signal update at 230th and Arata Road
  • Schedule: Wildish Standard Paving was selected as lowest responsible bidder and contract execution is in process. Construction will start in mid to late spring and run through fall 2018.
  • Traffic: There will be lane closures and one-way traffic during construction.
  • Website: www.multco.us/arata

In Design Phase

NE 238th Dr. Safety Improvements (NE Halsey St. to NE Glisan St.)

This project will make it easier for trucks to navigate the curve on this steep section of 238th Drive in Wood Village. It will improve access for other modes of transportation, including pedestrians and bicyclists.

  • Traffic: The construction traffic plan will be developed during the design, which recently began.
  • Schedule: Design work began in late spring 2017 and will continue in 2018, with a public meeting planned in spring 2018. Construction could begin in spring or summer 2019.
  • Website: multco.us/238th

Learn More

For more information on these and other Multnomah County road projects:

  • Visit multco.us/roads/road-projects
  • Follow us on Twitter @MultCoRoads
  • Call 503-988-5050, email transportation@multco.us